Bay Geeks Guide · Business Start 8 weeks out

Moving Offices? The IT Checklist

Most office moves go wrong in the same two places: the internet is not live on the first Monday, and the network closet was an afterthought until the furniture was already in. Both are fixed by starting the IT list the week the lease is signed, not the week of the truck.

We have moved offices for law firms, medical practices, assisted living communities and shops around St. Petersburg and Clearwater since 2004, and the pattern holds: the physical move takes a weekend, the IT part takes eight weeks of small decisions. Here is the list in the order the decisions have to be made, with the one thing to do first at each step.

The Short Version

Order the internet the day you sign. Walk the space with a floor plan and mark every drop before the cabling contractor comes, and have the cabling done before the furniture. Back up everything and test a restore before the truck. Bring the network up before the people. Then spend the first week fixing printers, Wi-Fi and the addresses you forgot to change.

Eight Weeks Out: The Decisions With Lead Times

Four Weeks Out: Build the New Space

01

Cabling before furniture

Drops are run, terminated, labeled at both ends and certified while the floor is empty. The same work after the desks arrive costs more and looks worse. Insist on labels and a test report; you will need both the first time a jack does not work.

02

Order the network gear to match the map

Firewall, switches with enough ports for the drops plus spares, and access points placed for the walls that are actually there. Power over Ethernet switches for the access points and cameras save a power outlet at every one of them.

03

Confirm the install dates in writing

Internet, cabling, phones, movers. Put them on one calendar in the order they have to happen. The internet install is the date everything else is measured from.

04

Back up everything and test a restore

Treat the move as a disaster-recovery rehearsal, because it is one. Every computer's cloud backup current, a full image of the server or network storage, and one restore actually performed and written down. See backup vs. disaster recovery.

05

Write the cutover plan

Who shuts down what on Friday, who carries the server, who is at the new space Saturday when the network comes up, and who tests what on Sunday. One page, with phone numbers.

06

List every place the address lives

Google Business Profile, the website, email signatures, invoices, the bank, insurance, the state filing, directory listings, the alarm company, the domain registrar. Change the ones that take time now; change the rest the day you move.

Move Weekend: Network First, People Last

  1. Friday: final backup, then shut down in order. Workstations first, then the server or network storage, then the network, then the UPS. Confirm the final backup completed before the first plug comes out.
  2. Photograph every cable before unplugging it. The back of the rack, the back of each desk, the printer. Thirty seconds with a phone saves an hour on Monday.
  3. Label and pack computers upright and padded. Monitors face to face with cardboard between. The server and any drives ride with a person, in a car, not on the truck.
  4. Saturday: the network goes in first. Modem, firewall, switches, access points, in that order, then test the internet from a laptop in every room before a single workstation is unpacked.
  5. Sunday: workstations, printers, phones, cameras. Each gets its drop, its power, and a sign-in test by the person who will use it. Printers get new addresses and get reinstalled on every machine, or they will be Monday's first call.
  6. Forward the old office phone and set the auto-replies if anything is not ready, so Monday is quiet instead of chaotic.

The First Week: What Breaks, and the Chance Nobody Takes

Expect three things: a printer that is still looking for its old address, a Wi-Fi dead zone the floor plan did not predict, and one computer that did not enjoy the truck. The drive monitoring on every maintenance plan usually flags that last one before it fails outright. Fix the dead zone with an access point, not a repeater; our Wi-Fi dead zones guide explains why.

Then take the chance a move gives you and almost nobody uses. Everyone who had a key, a door code or a Wi-Fi password at the old building still has it. Change the Wi-Fi password, retire the old door codes, and run the offboarding checklist for anyone who left during the last year and was never fully removed. Turn on multi-factor sign-in for every account while people are already expecting things to be different. A new office is the easiest day of the year to raise the security bar, because nobody is attached to how it was.

WhoOwnsAsk them for
Internet providerThe circuit to the buildingInstall date in writing; the handoff location in the suite
LandlordBuilding rules, access, the riserApproval for low-voltage work; after-hours access on move weekend
Cabling contractorDrops, termination, labelsLabels at both ends and a certified test report
MoversFurniture and boxesNothing that holds data: the server and drives travel with you
Phone providerNumbers and the portA port date that is not move weekend
Bay GeeksThe network, the computers, the cutoverThe floor-plan walk, the gear list, Saturday at the new space

Quick Self-Check

QuestionIf “no” or “not sure”...
Is the internet ordered, with an install date in writing?Do it today
Does a floor plan show every drop you need?Walk it this week
Has anyone restored a file from backup this month?Before the truck
Is there a cutover plan with names and phone numbers on it?Worth a call
FIXED ✓

Moving in the Next Three Months?

We walk the new space with you, mark the drops, size the network, bring it up before the furniture arrives and run the cutover weekend. Start with a 15-minute call and we will tell you what the lease date actually allows.

Frequently Asked Questions

How far ahead should I order internet for a new office?

Eight weeks is comfortable for a standard business connection in Pinellas. If the building has never had fiber, the provider may have to build to it, and that can take longer than the lease allows. Order first, before the furniture, and ask for the install date in writing.

Should we move the old server or replace it?

A move is the cheapest moment to replace anything that is out of support, because the downtime is already scheduled. If the server is on supported hardware and software, move it with a tested backup in hand. If it is not, migrate to the replacement before the move and carry the old one as a spare.

The new space already has network jacks. Do we need new cabling?

Test them first. Jacks in an older suite are often untested, unlabeled, or wired to a closet nobody can find, and some are not even Cat5e. A certified test of every drop costs less than one afternoon of troubleshooting a printer that will not connect. Add drops for the desks, printers, access points and cameras the test did not cover.

Can our staff work from home during the move?

Yes, if email and files are in Microsoft 365 or Google Workspace and the plan says so in advance. The office network can be down from Friday afternoon to Monday morning without anyone noticing, as long as the phones are forwarded and the one person who needs the server knows it is offline.

Employee Offboarding Checklist

What to do the day someone leaves, before anything gets deleted.

Hurricane Season IT Checklist

Before the storm, during the outage, and the surge on the way back up.

Backup vs. Disaster Recovery

RPO and RTO in plain English, and why your cloud apps still need a backup.

Who Owns Your Domain?

The registrant on record owns it, not the person who pays the invoice. How to check.

All guides →

📞 727-579-4335  ·  ✉️ support@baygeeks.com  ·  Privacy Policy  ·  Terms of Service

Call Now Schedule